Booster Set Replacement Project
Our customers had three booster sets that were at end of life expectancy and had obsolete parts.
Our customers had three booster sets that were at end of life expectancy and had obsolete parts.
The 11-storey building has recently undergone a major HVAC refurbishment and Pumptec Engineering were asked to provide a proposal for the project.
Following an ongoing concern with the vibration levels on the Primer Extract Fan, Pumptec were asked to confirm the problem initially.
At one of the main office buildings of a large financial institution, we were asked to survey the existing air handling units as the on-site maintenance team had noticed that the dampers were not operating properly.
The scope of works was to replace the old fan motors with new energy efficient motors over 5 weekends to minimise downtime as these units provided cooling and heating to critical areas.
Pumptec were recently asked to attend site to an international aerospace company to survey a badly vibrating fan assembly.